Port Said East Container Terminal project phase I

Owner
Suez Canal Container Terminal (SCCT)
Main Contractor
ARCHIRODON Constructions (overseas) Co.
Period
June 10, 2004 to Mar. 31, 2006
Total Value
28 million L.E.

Scope of Work
  • (Work area = 600,000 m2)
  •  Excavation including dewatering of unsuitable material to the depth to expose the basal sand of total quantity = 1.2 Million m3.
  •  Backfill and compaction with general fill site material.
  • Supply place and compact imported general fill material as defined in the specification from approved sources off site of total quantity = 1.3 million m3.    
  • Supply lay and compact Sand Cement-batch mixed (0.44m) thickness for paving of total quantity = 350,000m3. 

    The minimum required productivity per day was:-
    * For excavation= 7000 m3/day
    * For Backfilling = 4000 m3/day