The earthworks for Cairo festival city

Owner
Cairo Festival City
Main Contractor
Al Futtaim - Carillion – Orascom Co. J.V.
Period
June.9, 2008 to Oct.9, 2008
Total Value
 6 million L.E

Scope of Work
  • Excavation up the retail district zone for area 79000 m2 and down to 14 m2 depths. Total excavation quantity 620,000 m3 and moving the excavated material to the dumping area including all access, haul roads and safety precautions for slopes and HSE requirement.
  • Excavation works was finished in 90 days and with excavation production reached to 12,000 m3/day (day shift only).